Once the critical path is known, everything else has room to move. Float measures how much, a Gantt chart shows it at a glance, and a histogram turns it into a staffing question.
6 original questions · 22 marks · the float, gantt charts and scheduling notes · Decision Mathematics 1
Every question here is written for this library rather than taken from a past paper. Write your answer out before opening the worked one: the answers award marks point by point, and the marks are easier to see when you have something of your own to compare against.
An activity has earliest start 6, latest finish 13 and duration 4. Find its total float.
Worked answer
Total float = latest finish − earliest start − duration = 13 − 6 − 4 = 3 days. Equivalently, the latest start is 9 and the earliest is 6. M1 for the subtraction, A1 for 3 days.For the seven-activity project, the critical activities are A, C, E and G, and the latest starts of B, D and F are 2, 8 and 10 with earliest starts 0, 3 and 5. State every total float.
Worked answer
A, C, E and G are critical, so each has float 0. B: 2 − 0 = 2. D: 8 − 3 = 5. F: 10 − 5 = 5. B1 for the four zeros, B1 for B, B1 for D and F.Explain why D and F, each with 5 days of float, cannot both be delayed by 5 days.
Worked answer
They lie on the same chain: F cannot start until D has finished. The five days is the slack available to the chain as a whole, not to each activity separately, which is what the word total in total float signals. Delaying D by five leaves F no room at all, and delaying both would push G, and so the whole project, five days late. B1 for the shared chain, B1 for the float belonging to the chain, B1 for the effect on the finish.The activities take 3, 5, 4, 2, 6, 3 and 2 days, one worker each, and the project lasts 15 days. Find the lower bound on the number of workers, and state the peak demand if every activity starts as early as possible.
Worked answer
Total work = 25 worker-days over 15 days, so the lower bound is 25/15 = 1.67, rounded up to 2 workers. At earliest start times B runs from 0 to 5, C from 3 to 7 and D from 3 to 5, so all three overlap between days 3 and 5 and the histogram peaks at 3, above the bound. Always round the bound up, whatever the decimal. M1 for 25/15, A1 for 2 workers, M1 for the overlap between days 3 and 5, A1 for a peak of three.Show how the peak can be brought down to two workers.
Worked answer
D has 5 days of float, so it can be delayed. Move D to run from day 5 to 7 instead of 3 to 5, which takes it out of the crowded stretch and leaves B and C alone there. F then runs from 7 to 10, within its own latest start of 10.
The demand is now A and B to day 3, B and C to day 5, C and D to day 7, E and F to day 10, then E alone and finally G. It never exceeds 2, which matches the lower bound, so the schedule is optimal and the project still finishes in 15 days. M1 for delaying D within its float, A1 for D from day 5 to day 7, A1 for F from day 7 to day 10, B1 for the demand never exceeding two.A project lasting 10 days consists of A (10 days) and B, C and D (6 days each), with no activity depending on any other and each needing one worker throughout. Find the lower bound on the number of workers, and show that the bound cannot be achieved.
Worked answer
Total work = 10 + 6 + 6 + 6 = 28 worker-days over 10 days, so the lower bound is 28/10 = 2.8, rounded up to 3 workers.
Suppose three workers were enough. One must spend the whole 10 days on A, since A occupies its worker from day 0 to day 10 and cannot be split. That leaves two workers for B, C and D. Each of those has only 10 days available, and having completed one six-day activity a worker has 4 days left, too few for another. So two workers can finish at most two of the three, and 4 workers are needed.
The lower bound assumes work can be divided freely and every worker kept busy. It is a floor, not a promise, and an answer that quotes the bound as the answer to a scheduling question has stopped one step early.
M1 A1 for the total work, A1 for the bound of three workers, M1 for tying one worker to A, A1 for showing two workers cannot cover B, C and D, A1 for four workers.
The same practice on paper: the printable workbook for this topic, questions and a worked answer book.
Practise float, gantt charts and scheduling one question at a time
The player marks nothing for you. It shows one question, waits, then shows the worked answer so you can mark yourself, and brings a question back sooner when it went badly.